A can do a piece of work in 10 days, B in 15 days. They work together for 5 days, the rest of the work is finished by C in two more days. If they get Rs. 3000 as wages for the whole work, what are the daily wages of A, B and C respectively (in Rs):

a) 200, 250, 300

b)  300, 200, 250

c) 200, 300, 400

d) None of these

View Answer
Option – b.