An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?

A) Additional resources using the contingency fund

B) Escalation approval to use contingency funding

C) Team overtime to meet schedule

D) Corrective action based on causes

View Answer
Option – D.