Construction Planning & Management MCQ Civil Engineering Questions

Construction Planning & Management MCQ Questions Answers – Civil Engineering


1) Mile stone chart is an improvement over

a) Bar chart

b) CPM scheduling

c) PERT scheduling

d) All the above

View Answer
Option – a)

2) Which of the following is a weakness of bar chart ?

a) interdependencies of activities

b) project progress

c) uncertainties

d) all of the above

View Answer
Option – d)

3) The process of inspiring the subordinates to do a work or achieve an objective is called as

a) Management

b) Supervision

c) Motivation

d) Communication

View Answer
Option – c)

4) Which of the following does not represent an activity ?

a) site located

b) Foundation is being dug

c) the office area is being cleaned

d) The invitations are being sent

View Answer
Option – a)

5) In a bar chart the vertical axis represents

a) Time

b) Types of activities

c) Number of labours

d) Various avtivities of the project

View Answer
Option – d)

6)Grader is used mainly for

Trimming and finishing

Shaping and trimming

Finishing and shaping

Finishing, shaping and trimming

View Answer
Option – d)

7) A critical path has

a) zero slack

b) minimum slack

c) maximum slack

d) infinite slack

View Answer
Option – b)

8) Which of the following earth moving machines has the shortest cycle time ?

a) Drag line

b) Hoe

c) Clam shell

d) Dipper shovel

View Answer
Option – d)

9) The independent float affects only

a) preceding activities

b) succeeding activities

c) the particular activity involved

d) None of the above

View Answer
Option – c)

10) Probability of finishing of a project earlier than expected time is

a) 100%

b) less than 50%

c) more than 50%

d) None of these

View Answer
Option – b)