In the Determine Budget processes the project schedule

A) is not one of the inputs to these processes.

B) is used to allocate the project budget to the various project activities.

C) is used to assign costs to the time period when the costs will be incurred

D) is used to determine the size of the contingency component of the budget after all scheduled costs are accounted for.

View Answer
Option – C.