1) Mile stone chart is an improvement over

a) Bar chart

b) CPM scheduling

c) PERT scheduling

d) All the above

View Answer
Option – a)

2) Which of the following is a weakness of bar chart ?

a) interdependencies of activities

b) project progress

c) uncertainties

d) all of the above

View Answer
Option – d)

3) The process of inspiring the subordinates to do a work or achieve an objective is called as

a) Management

b) Supervision

c) Motivation

d) Communication

View Answer
Option – c)

4) Which of the following does not represent an activity ?

a) site located

b) Foundation is being dug

c) the office area is being cleaned

d) The invitations are being sent

View Answer
Option – a)

5) In a bar chart the vertical axis represents

a) Time

b) Types of activities

c) Number of labours

d) Various avtivities of the project

View Answer
Option – d)

6)Grader is used mainly for

Trimming and finishing

Shaping and trimming

Finishing and shaping

Finishing, shaping and trimming

View Answer
Option – d)

7) A critical path has

a) zero slack

b) minimum slack

c) maximum slack

d) infinite slack

View Answer
Option – b)

8) Which of the following earth moving machines has the shortest cycle time ?

a) Drag line

b) Hoe

c) Clam shell

d) Dipper shovel

View Answer
Option – d)

9) The independent float affects only

a) preceding activities

b) succeeding activities

c) the particular activity involved

d) None of the above

View Answer
Option – c)

10) Probability of finishing of a project earlier than expected time is

a) 100%

b) less than 50%

c) more than 50%

d) None of these

View Answer
Option – b)

11) In PERT analysis, event means

a) start or finish of a task

b) time taken for a task

c) end of an activity

d) work involved in the project

View Answer
Option – a)

12) The most likely time (m) is ‘mode’ of the

a) Normal distribution

b) Beta distribution

c) Bionomial distribution

d) None of the above

View Answer
Option – b)

13) Which of the following represents the reduction in duration ?

a) Crashing

b) Negative slack

c) Variance
d) All of the above

View Answer
Option – a)

14) Updating may result in

a) change of critical path

b) decrease of project completion time

c) increase of project completion time

d) all of the above

View Answer
Option – d)

15) The CPM network is updated

a) At regular intervals

b) At fixed times

c) At any time

d) Whenever there is difference in the planned and actual performance

View Answer
Option – d)

16) Which of the following earth moving machines has the shortest cycle time ?

a) Drag line

b) Hoe

c) Clam shell

d) Dipper shovel

View Answer
Option – a)

17) For a given size of bucket, the ideal output of a dragline will be least in

a) moist loam

b) Sand and gravel

c) Good common earth

d) Wet sticky clay

View Answer
Option – d)

18) For three-dimensional movement of a weight, which one of the following is most suitable ?

a) Chain hoist

b) Winch

c) Crane

d) Jack

View Answer
Option – c)

19) Which of the following earth moving machines has the shorter cycle time ?
a) Drag line

b) Hoe

c) Clam shell
d) Dipper shovel

View Answer
Option – d)

20) The basic action involved in sheep foot rolling is

a) kneading

b) pressing

c) tamping

d) vibration

View Answer
Option – a)

21) The working range of a crane is limited horizontally for maximum lift only by

a) boom length

b) length of hoist cable

c) length of jib

d) counter weight

View Answer
Option – a)