P alone can do a piece of work in 24 days. The time taken by P to complete one-third of work is equal to time taken by Q to complete half of the work. How many days are required to complete by P and Q working together ?

A) 9 3/5 days

B) 7 days

C) 6 3/7 days

D) 8 days

View Answer
Option – A.

Similar Questions