The project life cycle can be broken into five phases that tend to overlap with each other frm one phase to another;however ,the control phase does not overlap with a specific phase. why?

A) Change control management is seperate from the other phases

B) Change control management has a plan that can be usede throughout the initiation, planning, execution, and closeout of the project

C) Because the project sponsor is responsible for change control management , the project manager is not involved with that phase of the project

D) Change control extends throughout the entire project from initiation to closeout

View Answer
Option – D.